If you have a frame time of 2 days and 3 hours. And it’s a single frame job (background plate) it will report the average frame time as 1 day and 1.5 hours.

Is this in the job statistics report, or in the job details panel?

If it’s the latter, can you archive the job and send it to us? We can import it into our repo and check if we see the same thing.

Thanks!
Ryan

Job Details (See attached)
ggreenwalt__3dsmax__LOUNGE_Couch_CamA_C02.02 __5351bda3b5b7e10938c41d22.zip (12.4 KB)

Thanks! It looks like Jon has already fixed this issue internally, so the fix should be included in the next beta release. It was just luck that he happened to be looking at the job details code this past week. :slight_smile: