Task Progress Bar - Maya

Hi, we’re not seeing any Progress bar updates in the Tasks window of the Monitor for Maya jobs. Tasks sit at 0% until they complete and move to 100%.

Works as expected for C4D jobs but not for Maya 2015/16 jobs.

We’re on Deadline Version: 7.1.0.32 R (cb265b604)

Just wondered whether this was a known limitation or a bug (or a problem with our set up)?

Cheers,
Chris

Same here on 7.1.2.0. In the slave logs as well Maya only seems to offer a progress update every 20%, would be nice if it could be forced to be more frequent.

Hello,

I do believe that we have made great strides in making sure our progress is reporting properly in several app, Maya included, with the 7.2 version which is in beta now. Are you able to test it?

Hi,

Apologies for delayed response! It looks like this is fixed in 7.1.2.1.

Thanks,
Chris