AWS Thinkbox Discussion Forums

Any way to easily total up QUE time on the farm?

Hey folks!

Runnings deadline 8, is there any good way to get a total “que hours” out?

Was thinking it would be nice knowing how many hours we have had jobs waiting in QUE before getting to be rendered?

Thanks
Rickard

Not built in. If I was curious, I’d copy the “submitted” time from all the queued jobs, paste it into a spreadsheet app, do a timespan and sum them all together.

You’ll want to make sure “Human readable copying” is turned off so you can use the data easier:

Screen Shot 2017-04-25 at 10.37.58 AM.png

hej Edwin,

Thanks for the reply. A question, when i pull statistic from deadline 5.2, i have a colum named “Start Date Time”

I don’t see this one in 8, have it been removed?

Would make the task easier to do.

Looking at things, it seems we compute all of of the completed job stats when a job completes (which should have been obvious to me :smiley:)

Can you use the active jobs list of this, or do you need every submitted job? I can throw a feature request in, but trying to get a workaround up front would be handy.

Privacy | Site terms | Cookie preferences