I have created 6 pools. I want to assign 3 of the 6 pools to a job.
Only one pool is selectable at a time.
Any workaround for this?
You can only assign two pools to a job, a primary and a secondary pools. You can find the setting under Deadline Monitor > Job Options > Modify Job Properties > General
- Pool: The pool that the job belongs to.
- Secondary Pool: If enabled, the job can fall back to the secondary pool, if there are machines available in that pool.
What if i assign 3 pools to a group.
Is it possible to assign only that specific group?