Hy guys!!!
I would like to know how can i do for to change the framerange of multiple jobs but without change the frame list? Because i’ve a lot jobs so maybe you have a solution for me. For the moment i do that job by job so its very long!!!
Thanks for your future answer
Loic
Hi Loic,
You might need to explain this a bit more, because frame range and frame list sound like the same thing to me.
We’re you perhaps referring to Frames Per Task? If so, then no, this currently cannot be separated from the Frame List. However, there’s no reason why this shouldn’t be supported, so I’ve logged this as a feature request.
Cheers,
Hy rrussell,
Yes i refering to frames per task. I have a lot of shot, so with diferent frame list, in deadline but i would like to all this job have the same framerange. for exemple: shoot 001 = 1…51
shoot 002 = 1…80
shoot 003 = 1…20
…
And i want to take all this job and change the task group size. But if i select all this job and if i do that, Deadline change all framelist of my jobs.
So you have answer at my question, and i do that manually!
Thank’s for this. And if you find a solution of this, let me know!!!
Cheers,
Loic