I have so far found only a couple of these jobs, but its pretty odd… it says in the task progress column that its rendering 1 task still, but in the tasklist, everything is complete…
I had one job like that in the queue for more then a week, it stayed that way
If you restart the Monitor, does the job now show up as complete? We think we found a bug yesterday where the task counts for the job object aren’t cached properly by the Monitor. They’re fine in the database though, which is why a restart of the Monitor fixed it for us. Just wondering if you’re seeing something similar.
Ill keep an eye on it and try if i find it again