Why did the task show “rendering” even though the task was completed? that cause it can’t render the next task.
Hello
Thanks for reaching out. I need to look at the Verbose Worker log to see what the Worker is doing after it marked the task as complete. Please follow below to collect logs/troubleshoot:
-
Enable verbose Worker logs from Deadline Monitor> Tools> Configure Repo Options> Application Data> Check off Worker Verbose logs option. Then restart the Worker to make verbose logs setting take effect immediately.
-
Reproduce the issue on just one render node by applying Machine Limit let it complete the task
Machine Limit and Machine Allow List/Deny List
Use the Machine Limit to specify the maximum number of Workers that can render your job at one time. Specify 0 for no limit. You can also force the job to render on specific Workers by using an allow list, or you can avoid specific Workers by using a deny list. See the Limit Documentation for more information.
-
Connect with the render node running this Worker renders 100% but the status still keeps rendering and provide the Worker logs from application logs folder/directory: Logs — Deadline 10.2.1.1 documentation <<< this is important to share logs from the application logs because those are the most verbose form
-
While you are connected with the render node follow the troubleshooting steps here: Troubleshooting — Deadline 10.2.1.1 documentation