Would be good to be able to prioritise the worker in a pool for a job. eg. for pool “redshift”, assign the machines with 4090s first.
Also, for maya redshift, if frames per task is greater than 1, the task progress updates incorrectly . after each frame, progress resets to 0 instead of continuing to 100%. eg. if it set to 2 frames, you will see progress go from 0-50% twice before it completes.
Think someone posted the 1 line fix, but would be good to have it officially implemented.
thanks